Project slides work | Computer Science homework help

  
Using the process that you developed in Group Project 1.  Build out a project using your new methodology.
The Project
Using your new methodology, SCC would like you to complete the following project:
Scope: The scope of the project consists of 9 applications
Below is key information necessary to complete your project
If you choose to leverage IRR, NPV, PBP, or PV you will use the information below:
  
Initial Development Cost (YR   0) 
Year 1 Income
Year 2 Income
Year 3 Income
Year 4 Income
Year 5 Income
 
Application 1
$                        100,000.00
$                 25,000.00
$             28,750.00
$        34,500.00
$        36,225.00
$        36,587.25
 
Application 2
$                        125,000.00
$                 30,000.00
$             36,000.00
$        39,600.00
$        40,392.00
$        41,199.84
 
Application 3
$                        150,000.00
$                 15,000.00
$             18,300.00
$        19,215.00
$        20,752.20
$        21,789.81
 
Application 4
$                          75,000.00
$                 15,000.00
$             19,500.00
$        20,865.00
$        22,116.90
$        23,222.75
 
Application 5
$                        135,000.00
$                 50,000.00
$             55,000.00
$        56,100.00
$        61,710.00
$        65,412.60
 
Application 6
$                        210,000.00
$                 62,000.00
$             71,300.00
$        72,013.00
$        72,733.13
$        75,642.46
 
Application 7
$                        175,000.00
$                 85,000.00
$           106,250.00
$    111,562.50
$    117,140.63
$    119,483.44
 
Application 8
$                        175,000.00
$                 60,000.00
$             73,200.00
$        74,664.00
$        80,637.12
$        83,056.23
 
Application 9
$                        130,000.00
$                 75,000.00
$             99,000.00
$    101,970.00
$    108,088.20
$    110,249.96
Given the critical nature of the project, the company has developed a high-level budget and potential income for each application. 

Year 0 is the      projected cost the company has estimated for the build of the      component.  This includes a 15% overhead cost for project management      work
Year 1-Year 5 is the      amount of revenue the company has estimated for the product
The Acceptable      Rate of Return for all projects with the company is 10%

If you choose to use Dot Matrix Voting or Monopoly Money, you will use the following information
  
Total Dots
Monopoly Money
 
Application 1
29
$                   4,487.00
 
Application 2
19
$                   5,797.00
 
Application 3
23
$                   3,280.00
 
Application 4
21
$                   3,942.00
 
Application 5
18
$                   4,792.00
 
Application 6
29
$                   4,659.00
 
Application 7
12
$                   4,579.00
 
Application 8
17
$                   2,071.00
 
Application 9
9
$                   3,177.00
Team Available – The company has identified the following individuals who will be available to support the application development.  Each individual can work on a single application.  
  
Application   Developer 1
$70.00   per hour
 
Application   Developer 2
$65.00   per hour
 
Application Developer 3
$50.00   per hour
 
Application   Developer 4
$65.00   per hour
 
1   Contractor (Application Developer)
$130.00   per hour
Manage a project

Describe the process      that your team will use to elicit and decompose the requirements for the      project
Develop a Project      Overview Statement document for the project
Create a WBS for the      project.  Remember your WBS is a deliverable base, so there should be      a section of your WBS that outlines our project management deliverables
 

Determine an updated      budget
Using the following      information develop a Gantt chart

  
Information in Months
 
Optimistic Estimate
Pessimistic Estimate
Most Likely Estimate
 
Application 1
11
13
12
 
Application 2
9
11
10
 
Application 3
12
14
13
 
Application 4
8
10
9
 
Application 5
13
16
14
 
Application 6
9
11
10
 
Application 7
8
10
9
 
Application 8
16
19
18
 
Application 9
15
18
17

Describe 2 strategies      you can use to bring the project timeline to 12 months.
Develop a team      agreement 
Using your defined      prioritization process, prioritize each application.
Identify at least      five stakeholders for your project and a communication strategy for each      individual. 
Identify at least      five risks to include both threats and opportunities associated with the      project.  For each risk, please include the following information:

·  

Impact
Probability
Description of the       risk
Mitigation Strategy
Describe the process      your team can use to determine if the projects are making the appropriate      revenue. 

Assignment Requirements:
There is no narrative paper required for this project, however, a “narrative PowerPoint slide” should be submitted, which should include an audio presentation by all the team members.
The PowerPoint slide should be submitted as a group to be graded. (Hint: each team member can record their piece of the presentation and the project manager can consolidate everything into one single file to be submitted. The entire audio presentation should not be more than 30 minutes, and should not be more than 25 slides.)
The slide deck should include the following:

Overview of the      Project Management Process
A pictorial review of      how requirements will be elicited and decomposed
Project Overview      Statement 
WBS for the project
Project Budget
Gantt Chart
Team Agreement
Overview of the      prioritization process and prioritization process
Stakeholders
Risks
Overview of the process      used to ensure appropriate revenue